1. Where will offshore generation connect to the onshore grid?
In the U.S., there are a limited number of locations that are well-suited to interconnect offshore generation to the existing onshore grid because of densely populated coastal communities, existing infrastructure and limited ocean access. In the last three years, OSW developers have submitted interconnection requests to these ideal points of interconnection, in some cases exhausting the available capacity (i.e., headroom) at those locations. When the headroom at a location is used, the location and its nearby electrical facilities will likely require costly upgrades to inject more power, making it much less attractive for future OSW interconnections.
This concept applies to the individual interconnecting substations, but it can also apply on a broader scale. For example, according to a published ISO-NE Economic Study report, the New England onshore grid likely has enough headroom to accommodate 5.8 GW of OSW without major 345-kV upgrades. This translates to approximately five or six utility-scale projects. After those interconnections are made, it could cost $1 billion or more for each additional OSW project to upgrade the grid for interconnection. New England states have already procured 4.7 GW of OSW, about one project shy of the estimated less-costly headroom.
Many have called for ideal interconnection locations to be reserved, prioritized and allocated to developers outside of the traditional framework: the first-come, first-served interconnection queue. Officials in New England states are taking action to address this issue in their area. On Sept. 1, 2022, five New England states along the Atlantic Ocean shoreline released a request for information (RFI) with an attached Modular Offshore Wind Integration Plan. This plan mentions that the participating states would control the efficient use of points of interconnection (POI). This control paired with the right planning would likely unlock much more total headroom across the system.
Beyond New England, some states have formulated policies to address this concern indirectly. For example, the New Jersey State Agreement Approach (SAA) will likely competitively procure a swath of transmission upgrades to the coastal electricity grid. The SAA epitomizes a state’s ability to drive OSW developers toward optimal POI by either strategically reinforcing areas of the transmission grid onshore or developing junctions offshore that tie to the desired onshore POIs. States should continue to take more responsibility to steward points of interconnection for the long-term benefit of the industry.
